Scylnx's metal shed has never been the same since
the roof collapsed under heavy snow a few years ago. |
Foundation and floor joists (Tue) |
Mudsill detail with ledge for siding |
Flooring 2/3 installed (Wed) |
Flooring complete; first wall framed (Thu) |
Second long wall framed (Fri) | Fourth wall framed with door opening (Fri) |
First roof truss off production line (Sun) |
One day's roof truss production ... 600 gusset nails (Sun) |
Entire wall frame erected in an hour ... it helps when everything is square (Mon) |
Took the rest of the day to attach and prime almost all of the wall panels (Mon) |
Half of trusses up and levelled, roof sheathing started (noon, Tues) |
|
Finished roof sheathing (Thur) .. starting to look like shed |
Finished felt and drip guards one side (Thur) .. in progress here |
First shingles - painfully slow (Fri) |
More shingles - getting hang of roof brackets (Fri) |
Felt paper on second side of roof - much faster (Sun) . |
Shingles finished first side (Sun) in time to be tested with 3" of rain in less than 24 hours Sunday afternoon - Monday morning. |
Scylnx laying shingles on second side of roof (Tues) |
Second side more than half done ... started ridge vent and shingles |
Ridge vent shingles closeup (Tues) |
Roof finished (Tues ) ta-da! |
Last updated 11/12/2005